Phase 7 (Oct 1 - Dec 31, 2008 - FY09Q1)

Notation: led-green completed led-blue work is in progress led-gray defer to next phase

WBS Deliverable Description Major Milestones Status Resource
1 P7 Integration Phase 7: deployment, validation Staff, Tier1 + Tier2 centers
1.1 ATLAS releases ATLAS releases via Pacball & DDM Nov 30 led-blue Xin, Fred
1.2 Space management Provisioned space token areas Nov 15 led-green Tier2
1.3 Fabric upgrades Compute and storage upgrades Nov 15 led-green led-blue led-gray Tier2
1.4 Network monitoring services US LHC network monitoring infrastructure, Perf-Sonar, etc Oct 31 led-green Networking group
1.5 Load tests 200/400 MB/s Read/write sustained BNL-Tier2 Nov 15 led-blue Networking group
1.6 File Catalogs LFC integration & migration Oct 15 led-green SubCommitteeLFC
1.7 Site certification Table Site certification and benchmarks registered Dec 31 led-blue all sites
1.8 Analysis Benchmarks 100/200/400 jobs, suite of templates Dec 31 led-blue Nurcan, Mark, Tier2
1.9 US ATLAS Facility clients US-specific support for various ATLAS and OSG clients for admins and physicists On-going led-green Marco
1.10 Summary Report Summary report Dec 31 led-green all

Calendar and Milestones


-- RobertGardner - 15 Oct 2008

About This Site

Please note that this site is a content mirror of the BNL US ATLAS TWiki. To edit the content of this page, click the Edit this page button at the top of the page and log in with your US ATLAS computing account name and password.


Attachments

 
Powered by TWiki
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback