| WBS | Deliverable | Description | Milestone | Status | Resource |
|---|---|---|---|---|---|
| 1 | P4 | Integration Phase 4: specification, deployment, validation | March 31 | Tier1 + Tier2 centers | |
| 1.1 | ATLAS releases | ATLAS releases via Panda in full production | March 1 | delayed | all |
| 1.2 | DQ2 site services | DQ2 upgrades | periodic | delayed | all |
| 1.3 | OSG services | Validation for OSG 1.0 | March 1 | delayed | all |
| 1.4 | Storage services | Storage services WAN and LAN optimized | March 15 | on-going | all |
| 1.5 | Monitoring services | RSV-SAM, RSV-Nagios | March 15 | done | all |
| 1.6 | PROOF/xrootd | Tier2 guidelines/prototype | Feb 1/Mar 1 | delayed | all |
| 1.7 | Load tests | Read/Write performance targets reached | weekly | on-going | all |
| 1.8 | File Catalogs | FTS integrated/deployed | Mar 15 | delayed | BNL |
| 1.9 | Accounting | Accounting validation for WLCG | monthly | done | all |
| 1.10 | Analysis Queues | Analysis queues in production w/ validation robot | March 1 | done | all |
| 1.11 | Site certification Table | Site certification and benchmarks registered | March 31 | done | all |
| 1.12 | Summary Report | Summarized report (interim) of P4 including procurement status | March 31 | done | all |