Phase 4 (January 1 - March 31, 2008 - FY08Q2)

WBS Deliverable Description Milestone Status Resource
1 P4 Integration Phase 4: specification, deployment, validation March 31 Tier1 + Tier2 centers
1.1 ATLAS releases ATLAS releases via Panda in full production March 1 delayed all
1.2 DQ2 site services DQ2 upgrades periodic delayed all
1.3 OSG services Validation for OSG 1.0 March 1 delayed all
1.4 Storage services Storage services WAN and LAN optimized March 15 on-going all
1.5 Monitoring services RSV-SAM, RSV-Nagios March 15 done all
1.6 PROOF/xrootd Tier2 guidelines/prototype Feb 1/Mar 1 delayed all
1.7 Load tests Read/Write performance targets reached weekly on-going all
1.8 File Catalogs FTS integrated/deployed Mar 15 delayed BNL
1.9 Accounting Accounting validation for WLCG monthly done all
1.10 Analysis Queues Analysis queues in production w/ validation robot March 1 done all
1.11 Site certification Table Site certification and benchmarks registered March 31 done all
1.12 Summary Report Summarized report (interim) of P4 including procurement status March 31 done all

-- RobertGardner - 14 Apr 2008

About This Site

Please note that this site is a content mirror of the BNL US ATLAS TWiki. To edit the content of this page, click the Edit this page button at the top of the page and log in with your US ATLAS computing account name and password.


Attachments

 
Powered by TWiki
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback