| WBS | Deliverable | Description | Milestone | Status | Resource |
|---|---|---|---|---|---|
| 1 | P3 | Integration Phase 3: specification, deployment, validation | Dec 31 | Tier1 + Tier2 centers | |
| 1.1 | ATLAS releases | ATLAS releases, deployment method, tests | Nov 15 | carryover | all |
| 1.2 | DQ2 site services | DQ2 0.4, 0.5 deployments | Oct 27 | done | all |
| 1.3 | OSG services | Deployment of OSG 0.8 ATLAS | Dec 1 | done | all |
| 1.4 | Storage services | Site backend storage services | Dec 1 | carryover | all |
| 1.5 | Monitoring services | FTS, RSV, SAM | Dec 15 | FTS, RSV done; SAM delayed | all |
| 1.6 | Logging services | Upgrade logging infrastructure with security | Nov 15 | dropped | all |
| 1.7 | Load tests | Read/Write performance targets reached | weekly | delayed/carryover | all |
| 1.8 | File Catalogs | Implementation of MySQL LRC | Nov 15 | deferred | BNL |
| 1.9 | Accounting | Accounting validation for WLCG | monthly | all but one site | all |
| 1.10 | Analysis Queues | Analysis queues established | Dec 1 | done | all |
| 1.11 | Site certification Table | Site certification and benchmarks | Dec 31 | done | all |
| 1.12 | Summary Report | Summarized report (interim) of P3 including procurement status | Dec 31 | done | all |