August-September 30, 2007 - FY07Q4

WBS Deliverable Description Milestone Status Resource
1 P2 Integration Phase 2: specification, deployment, validation Sep 30 Rev 10/05/07 Tier1 + Tier2 centers
1.1 ATLAS releases ATLAS releases, deployment method, tests Sep 15 Panda-installer deferred all
1.2 DQ2 site services DQ2 testbed and validation processes Sep 30 delayed by DQ2 0.4 slippage BNL, UTA,
1.3 OSG services ATLAS Validation on ITB 0.7 (for OSG 0.8) Sep 30 complete BNL, UC, OU
1.4 Storage services Site backend storage services Sep 15 deferred BNL, MWT2, AGLT2
1.5 Monitoring services FTS and NDT focus; Nagios-based and others Sep 15 initial work complete all
1.6 Logging services Upgrade logging infrastructure with security Sep 1 deferred all
1.7 Load tests Control framework; throughput metrics established Sep 1 - Sep 30 initial work complete all
1.8 File Catalogs Evalution of file catalogs for sites LRC Sep 19 - Sep 30 survey complete, no decision all
1.9 Accounting Accounting validation for WLCG Sep 19 - Sep 30 complete all
1.10 Site certification Table Site certification and benchmarks Aug 7- Sep 30 in progress all
1.11 Summary Report Summarized report (interim) of P2 including procurement status Sep 30 complete all

-- RobertGardner - 16 Jan 2008

About This Site

Please note that this site is a content mirror of the BNL US ATLAS TWiki. To edit the content of this page, click the Edit this page button at the top of the page and log in with your US ATLAS computing account name and password.


Attachments

 
Powered by TWiki
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback