| WBS | Deliverable | Description | Milestone | Status | Resource |
|---|---|---|---|---|---|
| 1 | P2 | Integration Phase 2: specification, deployment, validation | Sep 30 | Rev 10/05/07 | Tier1 + Tier2 centers |
| 1.1 | ATLAS releases | ATLAS releases, deployment method, tests | Sep 15 | Panda-installer deferred | all |
| 1.2 | DQ2 site services | DQ2 testbed and validation processes | Sep 30 | delayed by DQ2 0.4 slippage | BNL, UTA, |
| 1.3 | OSG services | ATLAS Validation on ITB 0.7 (for OSG 0.8) | Sep 30 | complete | BNL, UC, OU |
| 1.4 | Storage services | Site backend storage services | Sep 15 | deferred | BNL, MWT2, AGLT2 |
| 1.5 | Monitoring services | FTS and NDT focus; Nagios-based and others | Sep 15 | initial work complete | all |
| 1.6 | Logging services | Upgrade logging infrastructure with security | Sep 1 | deferred | all |
| 1.7 | Load tests | Control framework; throughput metrics established | Sep 1 - Sep 30 | initial work complete | all |
| 1.8 | File Catalogs | Evalution of file catalogs for sites LRC | Sep 19 - Sep 30 | survey complete, no decision | all |
| 1.9 | Accounting | Accounting validation for WLCG | Sep 19 - Sep 30 | complete | all |
| 1.10 | Site certification Table | Site certification and benchmarks | Aug 7- Sep 30 | in progress | all |
| 1.11 | Summary Report | Summarized report (interim) of P2 including procurement status | Sep 30 | complete | all |