Plan to dump entire LRC to file and begin long-term import into existing test LFC instance (Hiro). This may take O(weeks). But once done, reloading this DB into another LFC instance will be quick: April 24
Final high-performance hardware for LFC at BNL is ordered, and expected by April 15th.
The idea is to test read and write performance with a fully-populated catalog.
If the tests look good, then the idea would be to do a second (and third) LRC dump, SELECTing only newly created entries since previous dump. Then import them into LFC.
Once (nearly) all entries are migrated, briefly halt production and do a final dump and load. Change BNL catalog type to LFC, and restart production. May 15
Plan for migration of LRC to LFC for Tier2s: May 21
Please note that this site is a content mirror of the BNL US ATLAS TWiki. To edit the content of this page, click the Edit this page button at the top of the page and log in with your US ATLAS computing account name and password.