FabricUpgradeP7
Introduction
Deployment (procurement, installation, testing, integration) of storage and compute server upgrades at each site.
Note: carried over from Phase 6:
Site plans
Tier 1
- Gridftp door upgrade: 5 new doors - completed.
AGLT2
- Target ~500TB of disk area (usable, after RAID6), (~396TB Tier-2, ~104TB Tier-3)
- Target ~2200 KSI2K? of cpu power (1800 Tier-2, 400 Tier-3)
MWT2
- Target: 300 TB raw storage
- Status (12/22/08) procured:
- MWT2_IU: 180 TB (raw), 160 cores
- MWT2_UC: 180 TB (raw), 192 cores
NET2
- 300T disk
- 34 dual quad nodes, 272 cores, ~760 kSI2K
SWT2
- 65 CPU units, 8 cores each at UTA
- 500-600 TB at UTA
- 100-150 TB at OU/Langston
WT2
- 320 cores Intel X5355 2.66Ghz
- 224TB usable
Milestone
- Original Phase 6 milestone was September 15, 2008; was deferred to Phase 7 due to purchasing delays.
--
RobertGardner - 22 Dec 2008