Upcoming release of dCache may not require srm - but the one that uses dccp.
Pilot still needs work. And other Panda developments.
All we can do is keep the old
AGLT2 - ATLASDATADISK - tested; 90 TB
SLAC - tested; 50 TB
BU - tested; 160 TB RAW
SW - setup, not tested; 60 TB
MW - working still.
RSV-SE probes
Xin - has tested RSV-SE probe in the new release, running on the SRM door node; works. Reports correctly to the RSV collector at the GOC. srm-ping, srm-cp
Would like to use existing infrastructure on OSG 0.8 gatekeepers.
for SRM-dCache - probe is ready.
for Bestman-xrootd - a minor issue needs to be resolved. Wei thinks won't be a problem. Sites will need to upgrade their bestman-xrootd. Wei will follow-up with Arvind and Alex.
CCRC08 news
Managed centrally - need to communicate the four endpoints that are ready to Stephane and Alexei.
Make sure old CCRC08 data is deleted - mainly for free space.
Heads-up minimal testing. AGLT2 trying it out now - Hiro sending additional information. Send feedback to Charles for official instructions. Gridsite must be enabled.
Analysis Queue Update
Analysis workshop next week at Argonne
Auto-site selection now working well - Marco's testing.
FDR1 reprocessing status? "This week", but nothing started.
Operations: Production (Mark, Kaushik)
After the dCache upgrade at BNL, there were issues with Panda Mover. US cloud was basically off. Issues cleared up on the BNL side.
On-going push to get last sites to autopilot. Transitioning BU last - all looks okay.
Next on list will be MWT2. Waiting for Paul - one of wrapper scripts need changes for dCache sites. Hopefully by end of week.
Then Tier3's
There may be pile-up jobs requiring lots of input files - that take only 30 minutes to run, but hours to stage input files. Not much we can do.
Some asymmetries seen in the load test measurements, under investigation.
Fixed problem of not properly killing iperf process.
Please send graphs to Shawn for next week's meeting.
Nagios monitoring subcommittee (Dantong)
No news.
Panda release installation issues (Xin)
Follow-up on the pacball-based method next week. No update.
OSG 1.0
ITB 0.9 deployment and validation in progress.
Sites at OU, UC, BNL all ready for VO testing.
Rob testing Panda submission.
Site news and issues (all sites)
T1: Hiro reports that storage is tight. Adding a 16 TB thumper today. Main implication is for FDR data and CCRC data transfers. Will be resolved by tomorrow.
AGLT2: all okay; some cpu drop at midnight last night.
NET2: all okay; SRM v2 up and running; still waiting from IBM a 10G replacement.
MWT2: all okay; running into some scaling issues with addition of new nodes (number of tcp sockets, etc). Upgraded all head nodes recently.
SWT2 (UTA): all okay; 1 day shutdown on 21st for electrical work on distribution panels.
SWT2 (OU): working on 10G cards and routing tests for the external network. FTS problems reported by Yuri? (Hiro thinks a minor problem.)