Phase 9 (April 1 - Jun 30, 2009 - FY09Q3)

Notation: led-green completed led-blue work is in progress led-gray defer to next phase

WBS Deliverable Description Major Milestones Status Resource
1 P8 Integration Phase 8: deployment, validation Staff, Tier1 + Tier2 centers
1.1 ATLAS releases ATLAS releases via Pacball & DDM   led-blue XZ
1.2 Fabric upgrades Compute and storage upgrades   led-blue  
1.3 Network monitoring services US LHC network monitoring infrastructure: validation   led-blue Networking group
1.4 Bestman validation Validate OSG/VDT based Bestman   led-blue OU, SLAC, BU, UTA
1.5 Squid servers at Tier 2 Conditions data access at Tier 2   led-blue all Tier 2
1.6 Load tests 200/400 MB/s and multi-site 1 GB/s Read/write sustained BNL-Tier2   led-blue Networking group
1.7 Storage Validation Disk, LFC, DQ2 catalog validation   led-blue all sites
1.8 Site certification Table Site certification and benchmarks registered   led-blue all sites
1.9 Analysis Benchmarks Stress test jobs validated   led-blue FacilityWGAP
1.10 US ATLAS Facility clients US-specific support for various ATLAS and OSG clients for admins and physicists   led-blue  
1.11 Summary Report Summary report   led-blue all

-- RobertGardner - 22 Apr 2009

About This Site

Please note that this site is a content mirror of the BNL US ATLAS TWiki. To edit the content of this page, click the Edit this page button at the top of the page and log in with your US ATLAS computing account name and password.


Powered by TWiki
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback