Phase 3 (October 1 - December 31, 2007 - FY08Q1)

WBS Deliverable Description Milestone Status Resource
1 P3 Integration Phase 3: specification, deployment, validation Dec 31 Tier1 + Tier2 centers
1.1 ATLAS releases ATLAS releases, deployment method, tests Nov 15 carryover all
1.2 DQ2 site services DQ2 0.4, 0.5 deployments Oct 27 done all
1.3 OSG services Deployment of OSG 0.8 ATLAS Dec 1 done all
1.4 Storage services Site backend storage services Dec 1 carryover all
1.5 Monitoring services FTS, RSV, SAM Dec 15 FTS, RSV done; SAM delayed all
1.6 Logging services Upgrade logging infrastructure with security Nov 15 dropped all
1.7 Load tests Read/Write performance targets reached weekly delayed/carryover all
1.8 File Catalogs Implementation of MySQL LRC Nov 15 deferred BNL
1.9 Accounting Accounting validation for WLCG monthly all but one site all
1.10 Analysis Queues Analysis queues established Dec 1 done all
1.11 Site certification Table Site certification and benchmarks Dec 31 done all
1.12 Summary Report Summarized report (interim) of P3 including procurement status Dec 31 done all

-- RobertGardner - 16 Jan 2008

About This Site

Please note that this site is a content mirror of the BNL US ATLAS TWiki. To edit the content of this page, click the Edit this page button at the top of the page and log in with your US ATLAS computing account name and password.


Attachments

 
Powered by TWiki
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback