| WBS | Deliverable | Description | Milestone | Status | Resource |
|---|---|---|---|---|---|
| 1 | P1 | Integration Phase 1: specification, deployment, validation | June 30 | Rev: 8/06/07 | Tier1 + Tier2 centers |
| 1.1 | ATLAS releases | ATLAS releases, deployment method, tests | June 1 | completed | all |
| 1.2 | DQ2 site services | Release specification and deployment of DQ2 0.3 | June 15 | completed | all |
| 1.3 | OSG services | OSG software deployment and integration | June 15 | completed | all |
| 1.4 | Storage services | Site backend storage services | June 15 | BNL, UC | all |
| 1.5 | Monitoring services | Panda, Gratia, FTS, NDT | June 15 | Gratia completed. NDT in progress | all |
| 1.6 | Logging services | DDM logging infrastructure | June 15 | completed at 6 sites | all |
| 1.7 | Site certification Table | Site certification specifications, records | June 15-30 | completed | all |
| 1.8 | Load tests | Series of dedicated and persistent tests - components of the full chain (DQ2+FTS+site services+backend storage); instrumented | June 15-30 | delayed | all |
| 1.9 | Summary Report | Summarized report (interim) of P1 including procurement status | June 30 | 8/6/07 | all |